30
COMMISSIONING
SECTION 4
CAUTION! DO NOT OPERATE THE WATER HEATER UNTIL THE
STORAGE VESSEL IS COMPLETELY FILLED WITH WATER, WITH WATER
RUNNING FROM ALL HOT TAPS.
Open the main gas supply cock after all connections to the gas control are completed
and test all connections, using proprietary leak detection fluid.
Lighting the Burner
1. Remove outer cover and slide inner cover to right. (On 63/62 and 84/87 Models, raise
the inspection port cover). Wait for 3 minutes for any unburnt gas to vent.
2. Turn the gas control knob to pilot.
3. Fully depress the gas control knob and the piezo igniter. With the pilot burner alight,
hold gas control knob in for 20 seconds. When gas control knob is released, the pilot
should remain lit. If not, repeat this operation.
4. Close and refit covers.
5. Set temperature indication dial to required temperature as follows:
Setting
0
1
2
3
Approx. Water
Temperature
104ºF (40ºC)
125ºF (52ºC)
143ºF (62ºC)
159ºF (71ºC)
6. Turn the gas control knob to ON and the burner should light. If not, wait for at
least 3 minutes and repeat from step 1.
STANDARD
RANGE
PERMANENT
PILOT MODELS
Fig 19.
Summary of Contents for 24/39
Page 11: ...11 INSTALLATION SECTION 3 Standard Range Hi FloRange Fig3a Fig3b ...
Page 19: ...19 INSTALLATION SECTION 3 Fig 6A Fig 7 ...
Page 23: ...23 INSTALLATION SECTION 3 WATER CONNECTIONS Fig 9 Fig 10 ...
Page 26: ...26 INSTALLATION SECTION 3 WATER CONNECTIONS Fig 13 Fig 14 ...
Page 29: ...29 INSTALLATION SECTION 3 WATER CONNECTIONS Fig 17 Fig 18 ...
Page 52: ...52 PARTS LIST AND ILLUSTRATIONS SECTION 9 Hi Flo Models 62 341 and 54 418 440 ...
Page 93: ...93 Notes ...
Page 94: ...94 Notes ...
Page 95: ...95 Notes ...