Full Height Tandem Installation Instructions
Installation Instructions [email protected] +1(909) 591-8431 www.alvaradomfg.com
Page 7
Installation Instructions
NOTE
Install the turnstile on a 8' x 6' level concrete slab. The
slab must be a minimum of 4" thickness. The turnstile may
only be installed on concrete. Do not install the turnstile on
asphalt.
NOTE
DIMENSIONS SHOWN ARE FOR MSTT MODELS. SEE
APPENDIX A AND B FOR OTHER MODELS.
Installation Locations
1.
Determine where the turnstile will be installed. Consider the overall footprint size of the unit when determining
the installation location (Figure 1). Once the installation location has been determined, use a chalk line to mark
the centerline of the turnstile.
2.
Determine and mark the centerline location for the OV, Rotos and Yokes (Figure 1).
NOTE
The overall height of the MSTT is 91.5". However, an additional 3" of clearance must be added for service and
maintenance.
Mark all center lines prior to installation.
Fig. 1
O
N
Turnstile
Center
Turnstile
Center
Roto
Centerline
54"
Yoke
Centerline
CL
Yoke
Centerline
94.50"
47.25"
47.25"
Roto
Centerline
OV Centerline
29.63"
29.63"
16.50"
16.50"
33.00"