Full Height Tandem Installation Instructions
Installation Instructions [email protected] +1(909) 591-8431 www.alvaradomfg.com
Page 17
Conduit Instructions
The installer can run power primary conduit to any of the locations shown in (Figure 25). Separate conduit can be
run to each side of the Top Channel lid, or conduit can be run to one side of the Top Channel lid and with connecting
conduit between the two junction boxes. In either case, conduit must be run all the way to each junction box.
Punch conduit hole at least 2.5" from the bottom of the Top Channel lid.
After completing primary and access control wiring, plug all unused routing holes in the Top
Channel.
Fig. 25
2.5"
.5"
3"
10"
10"
Power
ON/OFF
Switch
2.5"
Conduit
Location
Conduit
Location
NOTES