6 Setting up and installation
AL HPM
6.1
Unpacking and setting up
When unpacking, check all parts for damage in transit. Damaged parts must not be used. In the event of any damage, notify
the transport company and relevant transport insurance company immediately.
A suitably qualified member of staff must unpack, clean and assemble the machine in accordance with the installation
instructions.
Goods must be stored and transported in the original packing. Avoid any loading or mechanical stress, in particular of
housings, shafts, bearing points, through foreign objects or inadmissible vibration. Goods may only be transported on the load
handling equipment provided for this purpose.
The machine must be set up safely on the floor so that it is easily accessible.
The machine must not be exposed to any heat radiation or technical magnetic fields. No stands for people or other heavy
objects may be attached to the machine. The machine must not be set up in traffic areas. It must be accessible for
maintenance and operation at all times.
Install the machine as near to the production tank as possible.
Lock the rollers to prevent uncontrolled movement of the machine.
6.2
Connecting the product pipes
The product inlet and outlet must be firmly and tightly connected to the tank’s circulation pipe (see Figure 7). Keep the product
inlet pipe (intake pipe) as short as possible and do not use a diameter smaller than the connection of the unit. Use bigger
diameters for increased viscosity in order to reduce the pressure drop on the suction side.