7 Commissioning
AL HPM
The operator must observe VDE standard 0530 when commissioning the machine.
The machine may only be operated by trained, authorised operating personnel. Never commission the machine if it is not
fully installed.
Before commissioning, remove all dirt and foreign objects from the machine and the connected pipes and tanks. Check that
machine rotor and stator are running freely and free from contact.
7.1
Connecting the AL HPM to a mixing tank
Before commissioning, the AL HPM must be permanently piped to a tank in which the powder solution is produced (see Figure
7, circulation pipe). Hoses approved for the operation may also be used.
Make sure that during operation, ideally, a back-pressure of approximately 2 bar is generated after the outlet of the HPM to
allow optimum powder intake (1 bar would also be possible). This can be achieved with the aid of an Isomix jet mixer (see
Figure 7) installed in the tank at the end of the circulation pipe. This has the advantage that optimum intermixing is achieved
inside the tank.
After mixing, the Isomix rotating jet mixer can also be used to clean the tank (CIP).
4302-0023
Figure 7
19