BOSS – Installation, Operation and Maintenance Manual
A l e n c o n S y s t e m s L L C - P a g e
|
35
Testing the BOSS using a DC source and a DC Load
To test the BOSS using a DC source and load, power flow must be unidirectional, if source
cannot behave as a load. The default direction of flow is BUS to BATT with BUS connected
to the source while BATT connected to the load. If direction needs to be changed, connect
the DC source to the BATT side and the load to the BUS side, Fig.31, and follow the same
procedure outlined below.
Alencon performs this test using Magna Power Supplies and Alencon’s very own variable
voltage DC load.
Figure 32: Basic setup for testing the BOSS with a DC voltage source and a variable
voltage DC load. BUS side is connected to the DC source
Figure 33: Basic setup for testing the BOSS with a DC voltage source and a variable
voltage DC load. BATT side is connected to the DC source.
Please follow the below sequence of instructions to interact with the BOSS
Read Alencon’s documentation.
o
Establish communication the PODD – refer PODD setup instructions
Power ON the BOSS – refer section 10.1
o
Battery side Auxiliary
o
24 V External Power Supply