Installation
2
Installation
2.1
General information
All hydraulic components are pre-mounted and piped on the supporting frame. All pipe parts and fittings at risk from
condensation are insulated against cold and steam.
Warning!
Assembly, electrical connection, supply connection, maintenance, commissioning and repair, etc. must only be
carried out by trained and authorised specialists.
2.2
Setup
Important!
Components that come loose during transport can lead to faults or damage.
The station must be checked for transport damage upon delivery.
The condition of the ground must be taken into account.
The station should be vertical, the level can be adjusted by the height-adjustable feet.
The station must be bolted to the floor at the feet in a vibration-decoupled manner.
Connect piping to the heat exchangers.
Make sure that no impurities get into the system.
Take into account the reverse flow principle.
Once the piping is complete, the system must be flushed out.
1
Air inlet
2
Air outlet
3
Media inlet
4
Media outlet
Fig.: Reverse flow principle