3. Pre-Installation
Good planning leads to a successful zone system installation. Before installing and
commissioning a zoning system, please complete the following listed tasks:
3.1
Decide how many zones (dampers) are to be controlled in the system.
3.2 Group zones according to customer’s requirements. Each group initially has
one zone but can have up to a maximum of four zones (Example: There
could be one or more zones going into a common area such as Kitchen/
Dining or Family/Dining room). Work out the total group number (Maximum
total group number in a system is 16).
NOTE
: It is important to test all cables before installation.
Testing all cables to be used before the start of the installation will save
considerable diagnostic time if the fully installed system is subsequently found
to have a problem. Cable testing is quick and easy with a Zonemaster Cable
tester available from Polyaire.
Cable Tester (Item: 657089)
Pre-Installation
Summary of Contents for AirTouch 2
Page 1: ...airtouch net au Installer Manual...
Page 4: ...4 Compatible Brands Compatible Brands...
Page 19: ...19 Zone Setting...
Page 67: ...67...