d-lab.2, d-lab.2plus, netlab.2plus: Preinstallation
Transport
AgfaPhoto
2005-05-01 / PN 04100_01
7
3 Transport
Printer and Paper Processor are supplied separately and can be pushed separately to the
installation site. The following prerequisites must be checked and satisfied prior to
delivery:
–
Doors at least 0.95 m wide and 1.85 m high
4 Operation
Site
4.1
Separation of the Food Section
CAUTION!
Food must not be contaminated by photo-chemicals, or the waste or the
emissions thereof (risk of poisoning).
The operation site of the Minilab must be kept separate from the sales and stock
area for foods and snacks, e.g. by a separating wall or facilities having a similar
effect.
4.2 Room
Requirements
–
Room height at least 2.15 m (for removal of racks)
–
Minimum floor load capacity 500 kg/m²
–
The floor and the walls should be easy to clean
–
Floor conditions:
–
preferably waterproof concrete
–
resistant to water and photo-chemicals
–
even (no inclination, uneven spots, etc.)