3.2.3 Preparation for start-up
Adjusting the shock absorber and the stop screw
1
Clamping screw
P1
Air connection (drive out)
2
Shock absorber
P2
Air connection (drive on)
3
5
Stop sleeve
SD-Holder
4
6
Slide
Application strip
Setting the shock absorber and the stop screw
Procedure:
1.
Apply compressed air to (P1), the slide is extended
2.
Loosen clamping screw (1a)
3.
Adjust position by turning the stop sleeve (3)
4.
Adjust shock absorber by turning (2)
5.
Tighten clamping screw (1a)
6.
Apply compressed air to (P2), the slide (4) is retracted
7.
Loosen clamping screw (1b)
8.
Set position by turning the stop screw (3)
9.
Adjust shock absorber by turning (2)
10.
Tighten clamping screw (1b)
4
P2
P1
P2
3
2
2
3
P1
5
5
6
1
1
Summary of Contents for CS 16/30
Page 10: ...CS 16 CS 20 OI vers 5 3 gb 20190312 9 2 1 4 Slide unit load factors CS 16 ...
Page 11: ...10 CS 16 CS 20 OI vers 5 3 gb 20190312 2 1 5 Preferred combinations CS 16 ...
Page 12: ...CS 16 CS 20 OI vers 5 3 gb 20190312 11 2 1 6 Slide unit load factors CS 20 ...
Page 13: ...12 CS 16 CS 20 OI vers 5 3 gb 20190312 2 1 7 Preferred combinations CS 20 ...
Page 19: ...18 CS 16 CS 20 OI vers 5 3 gb 20190312 3 1 8 Dimension CS 16 ...
Page 20: ...CS 16 CS 20 OI vers 5 3 gb 20190312 19 3 1 9 Technical data CS 16 ...
Page 21: ...20 CS 16 CS 20 OI vers 5 3 gb 20190312 3 2 0 Dimension CS 20 ...
Page 22: ...CS 16 CS 20 OI vers 5 3 gb 20190312 21 3 2 1 Technical data CS 20 ...
Page 42: ...CS 16 CS 20 OI vers 5 3 gb 20190312 41 4 1 2 Accessories for CS 16 CS 20 module ...
Page 44: ...CS 16 CS 20 OI vers 5 3 gb 20190312 43 ZA intermediate stops for the CS 16 CS 20 ...
Page 48: ......