6.11 SETTING THE PRE-HEATING PROCEDURE FOR RADIANT PANELS (FLOOR DEBUG)
At the commissioning parameter setting page, by touching “Floor debug”, the con-
trol panel will access to the corresponding setting page.
Start
Floor debug: On
Segments: 2
Period 1 temp: 25°C
Segment time: 12H
∆T of segment: 5°C
After accessing the “Floor debug” function, you can activate or deactivate any pos-
sible procedure for pre-heating the radiant panels. This procedure creates a heating
cycle during which the temperature is kept stable for a certain time (period), then
increased by a value equal to ΔT indicated, and kept there for the next period. This
temperature increase and hold procedure will be repeated for the number of peri-
ods specified.
Floor debug
Number
Name
Displayed name
Range
Default
Accuracy
1
Floor debug switch
Floor debug
On/Off
Off
/
2
Quantity of segments
Segments
1~10
1
1
3
Temperature of the first segment
Period 1 temp
25~35°C
25°C
1°C
4
Duration of each segment
Segment time
12~72 hours
0
12 hours
5
Temperature difference of each segment
ΔT of segment
2~10°C
5°C
1°C
At the end, press the button at the top right to start (or interrupt) the pre-heating
cycle.
Note:
— This function can be activated only when the unit is turned off. When it is done
with the unit keeping "On", a warning will appear telling you to turn off the
unit first;
— When this function has been activated, “On/Off” operation will be deactivated.
By pressing On/Off, a warning will appear telling you to turn off the function;
— During the execution of this function, all other functions are disabled;
— Upon power failure, function will back to “Off” and the runtime will be zeroed;
— When “Floor debug” has been activated, “T-floor debug” and “Debug time” can
be viewed;
— When “Floor debug” has been activated and works normally; the corresponding
icon will be displayed at the upper side of the menu page;
— Before activating “Floor debug”, make sure “Segment time” of each segment is
not zero. If so, a warning will appear telling you that the time is wrong. In this
case, “Floor debug” is allowed to be activated only when “Segment time” has