SAFETY PRECAUTIONS
1-2
CAUTION
Many soaps used for gas pipe leak
testing are corrosive to metals. The
piping must be rinsed thoroughly with
clean water after leak checks have
been completed.
CAUTION!
DO NOT use this boiler if any part has
been under water. Call a qualified
service technician to inspect and
replace any part that has been under
water.
1.2 EMERGENCY SHUTDOWN
If overheating occurs or the gas supply fails to
shut off, close the manual gas shutoff valve
(Figure 1-1) located external to the unit.
IMPORTANT
The Installer must identify and
indicate the location of the emergency
shutdown
manual
gas
valve
to
operating personnel.
1.3 PROLONGED SHUTDOWN
After prolonged shutdown, it is recommended
that the startup procedures in Chapter 4 and the
safety device test procedures in Chapter 6 of
this manual be performed, to verify all system-
operating parameters. If there is an emergency,
turn off the electrical power supply to the
AERCO boiler and close the manual gas valve
located upstream the unit. The installer must
identify the emergency shut-off device.
MANUAL GAS SHUTOFF VALVE
VALVE OPEN
VALVE CLOSED
Figure 1-1. Manual Gas Shutoff Valve
IMPORTANT – FOR MASSACHUSETTS INSTALLATIONS ONLY
Boiler Installations within the Commonwealth of Massachusetts must conform to the following
requirements:
•
Boiler must be installed by a plumber or a gas fitter who is licensed within the Commonwealth of
Massachusetts.
•
Prior to unit operation, the complete gas train and all connections must be leak tested using a
non-corrosive soap.
•
If a glycol solution is used as anti-freeze protection, a backflow preventer must be installed
upstream of the Fill/Makeup Valve.
•
The vent termination must be located a minimum of 4 feet above grade level.
•
If side-wall venting is used, the installation must conform to the following requirements
extracted
from 248 CMR 5.08 (2):
(a) For all side wall horizontally vented gas fueled equipment installed in every dwelling, building or
structure used in whole or in part for residential purposes, including those owned or operated by the
Commonwealth and where the side wall exhaust vent termination is less than seven (7) feet above
finished grade in the area of the venting, including but not limited to decks and porches, the following
requirements shall be satisfied:
Summary of Contents for Benchmark 3.0LN Series
Page 6: ...iv ...
Page 8: ...B ...
Page 42: ...INITIAL START UP 4 8 ...
Page 80: ...A 6 ...
Page 84: ...B 4 ...
Page 86: ...C 2 APPENDIX C ...
Page 93: ...APPENDIX F APPENDIX F F 1 ...
Page 94: ...APPENDIX F F 2 ...
Page 95: ...APPENDIX F F 3 ...
Page 96: ...APPENDIX F F 4 ...
Page 97: ...APPENDIX F F 5 ...
Page 98: ...APPENDIX F F 6 ...
Page 99: ...APPENDIX F F 7 66034 ...
Page 100: ...APPENDIX F F 8 ...
Page 101: ...APPENDIX F F 9 ...
Page 102: ...APPENDIX F F 10 ...
Page 103: ...APPENDIX F F 11 ...
Page 104: ...APPENDIX F F 12 ...
Page 105: ...APPENDIX F F 13 ...
Page 106: ...APPENDIX F F 14 ...
Page 107: ...APPENDIX G APPENDIX G G 1 ...
Page 108: ...APPENDIX G G 2 ...
Page 109: ...APPENDIX G G 3 ...
Page 110: ...APPENDIX G G 4 ...
Page 111: ...APPENDIX G G 5 ...
Page 112: ...APPENDIX G G 6 ...
Page 113: ...APPENDIX H APPENDIX H H 1 ...
Page 114: ...APPENDIX H H2 ...
Page 115: ...APPENDIX H H 3 ...
Page 116: ...APPENDIX H H 4 ...
Page 117: ...APPENDIX H H 5 ...
Page 118: ...APPENDIX H H 6 ...
Page 119: ...APPENDIX H H 7 ...
Page 120: ...APPENDIX H H 8 ...
Page 122: ...APPENDIX I I 2 ...
Page 126: ...NOTES ...