Installation
Version:1.3
GSS0608
Page
51
of
72
7.5.3 Installing the communication cabling
The procedure described in the following for assembling the storage system is to be observed under all
circumstances. The designation on the SRB modules is CAN-BUS1 for the input and CAN-BUS2 for the
output to the next module. The module label can be found imprinted on the front label of the module.
F
IGURE
29:
A
TTACHING THE COMMUNICATION CABLE
-
1
Communication cable 1 (short)
•
Connect the communication
cable from SRC4310 to the first
CAN-BUS1 battery module.
F
IGURE
30:
A
TTACHING THE COMMUNICATION CABLE
-
2
Communication cable 2
•
Connect the next communication
cable from the first to the second
battery module CAN-BUS1.
1
2
Summary of Contents for StoraXe PowerBooster GSS0608
Page 1: ...StoraXe PowerBooster Compact storage system GSS0608 ...
Page 4: ......
Page 14: ...Preliminary information Page 10 of 14 GSS0608 Version 1 3 6 Bottom view of unit ...
Page 15: ...Preliminary information Page 11 of 14 GSS0608 Version 1 3 7 Checklist for commissioning ...
Page 16: ...Preliminary information Page 12 of 14 GSS0608 Version 1 3 ...
Page 21: ......
Page 22: ......
Page 118: ......
Page 120: ......
Page 121: ......
Page 122: ......
Page 123: ......
Page 124: ......
Page 125: ......
Page 126: ......
Page 127: ......
Page 128: ......
Page 129: ......
Page 138: ......
Page 139: ......