Controller interface tests
Description
Use these tests to check
- the output voltage of the channel for recording
- the communication functions of the input/output relays for the
channel.
- proper operation of the front panel buttons
- the RS232 protocol.
Accessing this test
Access :
SET/6. DAC
Connect a voltage measuring device to the recorder output.
- Press
ENTER
button to confirm.
The voltage displayed is 10.0 (Volts) (max value).
- Use the
buttons to select a different output voltage (10V to
0.1V).
Check that the measured voltage is the same as that displayed on the
controller.
Leaving this test
Press
to get back to the previous screen.
Verification of recorder
output voltage
The relays can be switched manually, independently of the pressure. It
is therefore a good idea to disconnect the cable attached to the Remote
connector.
Input/output relay
switching test
As soon as you press the
ENTER
button, the SP1 relay switches to the “ON”
position.
Accessing this test
Access :
SET/7.IO
Use the
buttons to change the output relay states and use an
appropriate device to check switching of the relays (ON/OFF).
n
Leaving this test
Press
to get back to the previous screen.