8
BEFORE USE
HANDLING OF THE PACKED MACHINE
The machine is supplied with suitable packing.
The total weight is 100 kg (221 lbs) max.
Packing dimensions:
Base:
84,5 cm x 57 cm (33”x22”)
Height:
85 cm (33")
Do not stack more than 2 machines.
UNPACKING OF THE MACHINE
1.
Remove the outer package.
2.
Loosen the two screws that fix the two
brackets to the machine.
3.
Unscrew the screws that fix the brackets to
the pallet and remove the brackets.
4.
Bring the handle bar into working position
(see under “MOVEMENTS OF THE HANDLE
BAR”) to lower the machine from the pallet
and pushing it forwards by the wheels
inclining the machine a little backwards to
avoid heavy contacts to the mechanical
parts.
5.
Keep the packaging for eventual transport
needs.
MOVEMENTS OF THE HANDLE BAR
The handle bar in the package arrives in closed
position.
To rotate the handle bar into one of the different
working positions:
1.
Pull up the release lever (1) near the handle
bars.
2.
Rotate the handle bar into the working
position while holding the release lever (1).
3.
Let go of the release lever (1) to lock the
handle bar.
Use the same procedure for further height
adjustment of the handle bar in order to find the
most comfortable working position.
CONNECTION BATTERIES
This machine is normally supplied with two
batteries already connected, AGM in series or one
Lithium battery, placed in its appropriate
compartment under the recovery tank.
In case the batteries need to be replaced, please
contact the authorized technical assistance.
The replacement of AGM batteries must be made
exclusively with batteries having the
identical
performances as the ones already installed, that
is
12V 34Ah
5
.
The replacement of Lithium batteries must be
made exclusively with
original spare parts.
With the connector (2) it is possible to connect
or disconnect the batteries.