A.07.370e - Edition 2.0
51
Installation
6
Installation
6.1 Main installation procedure
1. Examine the pre-installation. See § 6.2.
2. Examine the required tools. See § 6.3.
3. Transport the cabinet to the correct location. See § 4.2.
4. Unpack the equipment. See § 4.3.
5. Examine the equipment. See § 4.1.
6. Remove the lower rear panel. See § 6.6.
7. Install the electrical connections:
- Switch off the power supply. See § 6.5.
- Install additional earthing. See § 6.8 or § 6.7.
- Connect the power input supply. See § 6.9, § 6.10 or § 6.11.
- Connect the output to the series circuit. See § 6.12.
8. Install the remote control connections. See § 6.13.
9. Install the panels. See § 6.14.
6.2 Check pre-installation
Table: 6.1
Pre-installation checklist
6.3 Required tools and equipment
6.3.1
Required safety items
- Protective gloves;
- Protective shoes.
WARNING
Always wear protective gloves and shoes when you do work on the equipment or the
series circuit.
WARNING
Make sure that the power is OFF when you install the equipment.
Checked
Item
The substation meets the general requirements.
The cables have been installed according to an applicable layout.
All the cables have enough slack to connect to the equipment.
All the cables meet the specifications.
For each equipment there is a power supply cable available.
For each equipment there is a remote control cable available.
For each equipment there is a series circuit cable available.
Summary of Contents for CRE 10
Page 1: ...A 07 370e Edition 2 0 Installation Manual Constant Current Regulator Type CRE ...
Page 14: ...14 A 07 370e Edition 2 0 Safety ...
Page 44: ...44 A 07 370e Edition 2 0 Inspection and transport ...
Page 64: ...64 A 07 370e Edition 2 0 Installation ...
Page 85: ...A 07 370e Edition 2 0 85 Technical data ...
Page 86: ...adbsafegate com ...