INTERLOCKS BETWEEN PANELS
APPAR ATUS CO NTRO L TESTING
60
1VLG5000 17 C
Step 2/11
On the protection relay LHMI (upstream circuit breaker such as the Incomer, Generator and
Bus tie receiving the ARCSARC trip signal) go to ->
Main Menu/Test/IED test
–
Test mode = IED test
The ready LED is flashing when the protection relay is in test mode.
Figure 92: Entering test mode
Step 3/11
On the protection relay LHMI (tested feeder) go to ->
Main Menu/Test/IED test
–
Test mode = IED test
The ready LED is flashing when the protection relay is in test mode.
Step 4/11
Close all circuit breakers in the relative section. Check all the circuit breakers status on the
protection relay LHMIs.
Figure 93: Single line diagram, the circuit breaker is closed and in the service position
Summary of Contents for UniGear Digital
Page 1: ...DISTRIBUTION SOLUTIONS UniGear Family UniGear Digital Commissioning and testing Guide...
Page 2: ......
Page 3: ...DISTRIBUTION SOLUTIONS UniGear Family UniGear Digital Commissioning and testing Guide...
Page 6: ......
Page 10: ......
Page 12: ......
Page 96: ......
Page 98: ...Visit us www abb com mediumvoltage Document Number 1VLG500017 Rev C...