The automatic voltage control for tap changer, parallel control TR8ATCC, if installed, may be
set to operate in Master Follower (MF) mode, or Minimise Circulating Current (MCC) mode. The
commissioning tests for each parallel control mode are addressed separately in the following
procedure.
Secondary injection of load current (I
L
) and secondary bus voltage (U
B
) equivalent quantities
are required during installation and commissioning tests. The test consists mainly of:
1.
Increasing or decreasing the injected voltage or current at the analogue inputs of the IED.
2.
Checking that the corresponding commands (Lower or Raise) are issued by the voltage
control function.
Setting confirmation is an important step for voltage control in the installation and
commissioning phase to ensure consistency of power systems base quantities, alarm/
blocking conditions and parallel control settings for each transformer control function.
Before starting any test, verify the following settings in PCM600 or the local HMI for TR1ATCC,
TR8ATCC and TCMYLTC and TCLYLTC.
•
Confirm power system base quantities
I1Base, I2Base, UBase.
Main menu/Settings/IED Settings/Control/TransformerVoltageControl(ATCC,90)/
TR1ATCC:x/TR8ATCC:x/General
and
Main menu/Settings/IED Settings/Control/TransformerVoltageControl(ATCC,90)/
TR1ATCC:x
.
•
Confirm that the setting for short circuit impedance
Xr2 for TR1ATCC or TR8ATCC is in
accordance with transformer data:
•
Short circuit impedance, available on the local HMI under Main menu/Settings/IED
settings/Control/TransformerVoltageControl(ATCC,90)/TR1ATCC:x/TR8ATCC:x/
Xr2.
•
Confirm that the setting for TCMYLTC or TCLYLTC is in accordance with transformer data:
•
Tap change timeout duration - effectively the maximum transformer tap change
time,
tTCTimeout, available on the local HMI under Main menu/Settings/IED
Settings/Control/TransformerTapControl(YLTC,84)/TCMYLTC:x/TCLYLTC:x/
tTCTimeout.
•
Load tap changer pulse duration - required length of pulse from IED to load tap
changer,
tPulseDur, available on the local HMI under Main menu/Settings/IED
Settings/Control/TransformerTapControl(YLTC,84)/TCMYLTC:x/TCLYLTC:x/
tPulseDur.
•
Transformer tap range,
LowVoltTap and HighVoltTap, available on the local HMI
under Main menu/Settings/IED Settings/Control/
TransformerTapControl(YLTC,84)/TCMYLTC:x/TCLYLTC:x/HighVoltTap and .
•
Load tap changer code type - method for digital feedback of tap position,
CodeType, available on the local HMI under Main menu/Settings/ IED settings/
Control/TransformerTapControl(YLTC,84)/TCMYLTC:x/TCLYLTC:x/CodeType.
Section 12
1MRK 502 067-UEN B
Testing functionality by secondary injection
212
Commissioning manual