Installation and Commissioning Flowchart
Task
See
Identify the frame size of your drive: R7 or R8.
“Technical Data / NEMA Ratings”
Plan the installation.
Check the ambient conditions, ratings, required
cooling air flow, input power connection,
compatibility of the motor, motor connection, and
other technical data.
Select the cables.
"Technical Data"
"Planning the Electrical Installation"
Option manual (if optional equipment is
included)
Unpack and check the unit.
Check that all necessary optional modules and
equipment are present and correct.
Only intact units may be started up.
“Mechanical Installation: Moving the Unit,
Before Installation”
If the converter has been non-operational for
more than one year, the converter DC link
capacitors need to be reformed. Ask ABB for
instructions.
Check the installation site.
“Mechanical Installation: Before Installation”
"Technical Data"
If the drive is about to be connected to an IT
(ungrounded) system, check that the drive is not
equipped with EMC E202.
“The ACS800-PC: Type Code.” For
instructions on how to disconnect the EMC
filtering, contact ABB.
Route the cables.
“Planning the Electrical Installation: Routing
the Cables”
Check the insulation of the motor and the motor
cable.
“Electrical Installation: Checking the Insulation
of the Assembly “
Install the drive. Connect the power cables. Connect
the control and the auxiliary control cables.
“Mechanical Installation, Electrical Installation,
Resistor Braking” (optional)
Check the installation.
"Installation Checklist and Start-Up"
Commission the drive.
"Installation Checklist and Start-Up"
,
appropriate firmware manual
Commission the optional brake chopper (if present).
"Resistor Braking"