7 Re-packing
7.1 Removal of the bushing from the transformer, draw rod
Procedure
1.
Install the lifting tool, refer to
Installation of lifting tools,
page
2.
Put the pull-through cord (12) through the
box-spanner (13).
NOTE!
The terminal on the pull-through
cord (12) has M8 threads.
NOTE!
Hitachi ABB Power Grids recommends
that the hydraulic jack is used for the
removal of the lower draw rod, refer to
Removal of the lower draw rod with bottom
contact from the bushing ,
page
steps 1 through 8.
G004924
3.
Apply Molykote Multilub to the thread on the
pull-through cord (12), then connect it to the
draw rod.
NOTE!
Or use a lubricant with equal properties
to Molykote Multilub.
G006960
Summary of Contents for 1ZSC902110-AAA
Page 12: ...12 Installation and commissioning guide 1ZSC000563 AAF EN REV 4 2021 06 23 ...
Page 18: ...18 Installation and commissioning guide 1ZSC000563 AAF EN REV 4 2021 06 23 ...
Page 78: ...78 Installation and commissioning guide 1ZSC000563 AAF EN REV 4 2021 06 23 ...
Page 82: ...82 Installation and commissioning guide 1ZSC000563 AAF EN REV 4 2021 06 23 ...