35/54
TLE Scalable Series 40 to 150 UL S1
UPS Installation Guide / REV-B
4.8.3
Battery cabinet connection to TLE Scalable Series 40 to 150
Note!
The installation and cabling of the Battery cabinet must be performed only by an ABB Service
Technician!
Before proceeding to “Battery cabinet” connection, follow the Safety rules concerning the Battery.
Refer to the “Safety prescriptions – Installation/ Battery” described on Chapter 1.
Make sure that the UPS is not powered and the “Battery breaker” is open (Pos. O).
Before closing the “Battery breaker” verify the correct polarity of the Battery connection.
Battery cabinet
Battery
1 Battery cabinet / 2 Battery cabinets / 3 Battery cabinets / 4 Battery cabinets
Dimensions (W x D x H)
29.80 x 29.50 x 75.00 inches / 757 x 750 x 1905 mm
40.00 x 29.50 x 75.00 inches (1016 x 750 x 1905 mm)
Type of cables connection
75°C rating; size per NEC Table 310.16 and/or all applicable national and local
codes (see also Section 4.7.4).
“Battery cabinet(s)”
must be located on left side of the UPS
.
The connecting cables (+/-/PE) are supplied with the Battery cabinet.
Connect the cables to UPS bus bars “+/-/PE” using
M8 bolts
with a torque wrench at
195 Lb-in / 22 Nm.
Note!
Check for sufficient floor loading capacity.
For further information please consult the “Installation, Operation & Maintenance Manual” of the
“Battery cabinet”.
Fig. 4.8.3-1 TLE Scalable Series 40 to 150 - Battery cabinet connection to TLE Scalable Series 40 to 150
+
Positive pole
-
Negative pole
PE
Battery cabinet ground
Attention!
It is mandatory to ground the Battery cabinet to UPS!
To meet standards concerning electromagnetic compliance, the connection between the UPS and
external Battery cabinet must be done by using a shielded cable or suitable shielded (metal)
conduit!
Battery
cabinet
+
Wiring shall comply
to local regulations !
To UPS
bus bars
-
PE (GND)
Q1
_+
PE
TLE
S_UL
_04
0-15
0_S
1_B
atte
ry c
abin
et_C
onn
ecti
on_AB
B_0
1US
EP
O
EP
O
-
+
XA
POWER MODULE 1
POWER MODULE 2
POWER MODULE 3
J35µP -
RS232
Q1
Output cables