August 2014
Added energy recovery wheel v-bank filter sizes. Added more detailed microchannel coil cleaning
instructions.
November 2014
Updated condensate drain pan section showing p-traps are no longer provided on the 26 and 31-
140 ton units, added the p-trap sizing section, added plenum fan set screws specifications, added
tandem compressor option for the 55, 65 and 75-140 ton units.
March 2015
Updated E cabinet unit clearances; the unit clearance for the back of the unit was updated to 100”
from the end of the unit.
Added
Tandem Circuited Variable Speed Compressor VFD Frequency
Range
Table
.
May 2015
Updated
Refrigerant to Water Heat Exchanger
section to state that a screen strainer is factory
provided ahead of the condenser inlet and a pressure relief device may be provided on the heat
exchanger.
July 2015
Removed 2” Throwaway Unit Filter-25% Efficient from Filter Replacement information. Table 4-
C Cabinet Unit Clearances
revised.
October 2015
Added Additional Gas Piping Considerations.
November 2015
Water Piping
and
Filter
sections were updated.
February 2016
Added
Freeze Stat Startup
section and updated
Phase and Brownout Protection Module
section.
March 2016
Updated Metal Mesh Pre Filter quantity for RN-E cabinet. Updated RN-D cabinet energy recovery
filters quantity and size for outside air preheat.
April 2016
Added the
Adjustable Fan Cycling Switch Procedure
section.
May 2016
Added the AAON Touchscreen Controller.
June 2016
Packaged Direct Expansion (DX) Units section was updated for clarification.
Summary of Contents for RN Series
Page 2: ......
Page 32: ...32 Figure 5 RN Series 6 8 and 10 ton Unit Isolator Locations ...
Page 33: ...33 Figure 6 RN Series 9 and 11 15 ton Unit Isolator Locations ...
Page 34: ...34 Figure 7 RN Series 16 25 and 30 ton Unit Isolator Locations ...
Page 35: ...35 Figure 8 RN Series 26 31 50 60 and 70 ton Unit Isolator Locations ...
Page 36: ...36 Figure 9 Steel Mounting ...
Page 102: ...102 Figure 56 Example 6 50 60 70 ton through the Base Gas Piping ...
Page 105: ...105 Gas Heater Operating Instructions Figure 58 Gas Heater Instructions ...
Page 129: ...Maintenance Log E Coated Coil ...