
16
Lifting and Handling the Unit
Before lifting unit, be sure that all shipping
material has been removed from unit.
Care should be taken if using spreader bars,
blocking or other lifting devices to prevent
damage to the cabinet, coil or fans.
Sealing
It is very important to keep outside air from
infiltrating the unit cabinet. Seal all piping
penetrations with Armaflex, Permagum, or
other suitable sealant. Also seal around drain
connections, electrical connections, and
other inlets where air may enter the cabinet.
This is especially important when the unit is
installed in an unconditioned area.
Cooling Equipment
Acceptable system design and installation
will include consideration as follows:
Piping from the condensing unit to the
indoor air handling unit is the responsibility
of the installing contractor.
Only clean “ACR” tubing should be used.
Piping should conform to generally accepted
practices and codes.
Care must be taken not to cross the circuits
on reheat systems.
Once piped, the interconnecting piping and
air handling unit
MUST BE
evacuated to
500 microns or less; leak checked and
condenser shutoff valves opened to allow
refrigerant flow to air handling unit. Charge
unit with R-410A refrigerant to the
recommended superheat/sub-cooling in the
Charging Refrigerant section of this manual.
Make sure air handling unit thermal
expansion valve bulb is mounted with
good thermal contact on the suction line
on a horizontal section, close to the
evaporator but outside the cabinet in the
4 or 8 o’clock position and well insulated.
Lines should be fastened and supported
according to local codes.
Heating Equipment
Hot Water Heating:
Water supply lines must be insulated,
properly fastened, drained and supported
according to local code requirements.
Electric Heating:
Installing Electric Heat Strip into the
Unit:
1.
Remove front control panel(s) of the unit
2.
Remove screws and panel covering heat
strip compartment
3.
Open the heat strip kit and remove
assembly from package
4.
Install strip heat into opening and secure
with 4 (four) screws
5.
Install breaker assembly on bracket and
secure with breaker with 4 (four) screws
6.
Make sure that breaker is in the
OFF
position
7.
Connect all control wires per wiring
diagram included in the unit
UNIT HANDLING
Incorrect lifting can cause damage to
the unit, injury or death. Lifting
equipment capacity should exceed
unit weight by an adequate safety
factor. Always test lift unit not more
than 24 inches high to verify proper
center of gravity lift point.
WARNING
Summary of Contents for F1-060
Page 31: ...31 ...
Page 36: ...36 Figure 8 Heat Pump Piping Diagram with Indoor Unit above Outdoor Unit ...
Page 37: ...37 Figure 9 Heat Pump Piping Diagram with Outdoor Unit above Indoor Unit ...
Page 40: ...40 Thermostat Installation and Wiring Figure 12 2 Stage Cooling with Electric Heat ...
Page 41: ...41 Figure 13 2 Stage Cooling with Heat Pump and Electric Heat ...
Page 42: ...42 Figure 14 2 Stage Cooling and Electric Heat with Hot Gas Reheat and Humidistat ...
Page 43: ...43 Figure 15 Main Control Board for Units Equipped with Modulating Hot Gas Reheat ...
Page 45: ...45 Figure 17 5kW Electric Heat ...
Page 46: ...46 Figure 18 10 kW Electric Heat ...
Page 47: ...47 Figure 19 15 kW Electric Heat ...
Page 48: ...48 Figure 20 20 kW Electric Heat ...
Page 49: ...49 Figure 21 25 kW Electric Heat ...
Page 55: ...55 ...