Code and description
Cause
Measure
F11
(blocking error)
Ionisation error
Ionisation measured with
a closed gas control valve
Defective gas control valve.
-
Make sure that there is no flame after
the gas control valve has closed.
-
If there is a flame, the gas control
valve must be replaced.
F19
(blocking error)
Supply voltage error
Three unsuccessful
ignition attempts.
There is not enough or too much supply
voltage during 60 seconds.
The measured voltage between live and
neutral must be 230 V
AC
(-15%,
+10%).
The supply voltage between live and
earth must be between 110 V
AC
and
230 V
AC
(-15%, +10%)
-
Make sure that the supply voltage on
the controller is correct.
-
If the supply voltage is above or below
the stated tolerance and the error
persists, contact your maintenance
and service engineer.
-
Install an isolating transformer.
F21
(lock out error)
Air proving switch error
Switch is not closed, while
fan runs during post purge
Damaged wiring/open circuit.
See measure of error
F03
- Switch is not
closed when fan is running during pre-
purge.
S02
(blocking error)
Sensor error
Open circuit from sensor 1
of the temperature sensor
Sensor is not (correctly) connected.
-
Make sure that the connector is
connected to J3.
-
Make sure that the wire is connected
to the sensor.
Damaged wiring and/or defective sensor. Replace the wiring and/or sensor.
S03
(blocking error)
Sensor error
Open circuit from sensor 2
of the temperature sensor
Sensor is not (correctly) connected.
-
Make sure that the connector is
connected to J3.
-
Make sure that the wire is connected
to the sensor.
Damaged wiring and/or defective sensor. Replace the wiring and/or sensor.
S12
(blocking error)
Sensor error
Short circuit in sensor 1 of
the temperature sensor
Short circuit in the sensor circuit.
Replace the wiring and/or sensor.
S13
(blocking error)
Sensor error
Short circuit in sensor 2 of
the temperature sensor
Short circuit in the sensor circuit.
Replace the wiring and/or sensor.
0312266_INNOVO_UKUK_
V5.1, 2022-07-12
79
Summary of Contents for Innovo IR 12-160
Page 6: ...6 ...
Page 13: ...User part 0312266_INNOVO_UKUK_V5 1 2022 07 12 13 ...
Page 14: ...14 ...
Page 16: ...16 User part ...
Page 18: ...18 User part ...
Page 24: ...24 User part ...
Page 27: ...Installation Maintenance and Service part 0312266_INNOVO_UKUK_V5 1 2022 07 12 27 ...
Page 28: ...28 User part ...
Page 36: ...36 Installation Maintenance and Service part ...
Page 56: ...56 Installation Maintenance and Service part ...
Page 58: ...58 Installation Maintenance and Service part ...
Page 70: ...70 Installation Maintenance and Service part ...
Page 83: ...0312266_INNOVO_UKUK_V5 1 2022 07 12 83 ...
Page 87: ...13 4 Electrical wiring diagram 0312266_INNOVO_UKUK_V5 1 2022 07 12 87 ...
Page 89: ...13 5 Declaration of conformity 0312266_INNOVO_UKUK_V5 1 2022 07 12 89 ...
Page 90: ......
Page 91: ......
Page 94: ...92 Installation Maintenance and Service part ...