Chapter 8 Installing Main Antenna Feeder System
F
IGURE
72 C
ONNECTION BETWEEN
D
IRECTIONAL
A
NTENNA AND
J
UMPER
E
ND OF STEPS
.
Hoisting Antenna and Feeder
Context
While hoisting antenna and feeder, comply with the following:
�
Installation personnel on the tower pulls rope upward and the
other personnel under the tower draws the rope to control an
ascending direction of antenna.
�
During hoisting, make sure no people standing under the goods
hung in the air. While walking out of the platform, installation
personnel must wear safe belts.
�
。
Some small metal goods or tools, for example, antenna fix-
ation clips and wrenches, should be put in a canvas tool bag,
sealed and then hoisted.
�
After hoisting goods to the platform on the top of tower, put
them in a secure position and take security measures.
�
The above method is adoptable for hoisting of other goods.
Steps
1. Install a fixed pulley on the top of tower.
2. Make a rope through the fixed pulley and tie knots with the
rope at the two ends of antenna.
3. Installation personnel on the tower and under the tower hoist
the antenna to the position of fixing antenna together.
Hoisting antenna is as shown in