Chapter 8 Installing Main Antenna Feeder System
i.
Install a fixed pulley at top of the tower the tower. Hoist the
rack onto the iron platform with one or two ropes through
the crown block. In addition, control an ascending direction
of rack with another rope.
ii. According to the installation drawing of antenna and feeder
in the engineering design drawing, confirm the installation
position of antenna rack.
iii. Extend the rack out of the iron platform and fasten it on
the tower body with U-shape fixation clips (connection bar
and U-shape bolt included), as shown in
.
F
IGURE
79 A
NTENNA
R
ACK
I
NSTALLATION
1.
Connection bar
2.
U-shape bolt
3.
Iron platform
iv. Connect guard bars of platform and connect bottom plates.
If it is inconvenient to connect the antenna rack with the
guard bars, weld them and make sure welding fastened.
Cover a layer of antirust paint on the all parts welded and
on the surface of rack.
2. Installing the directional antenna
i.
According to the engineering design drawing, make sure
the installation direction of antenna.
ii. Hoist the antenna to a specified position with a block and
rope. Make sure the antenna within the protective area of
arrester.
iii. Install a fixation rack of antenna and make the rack col-
lapsed, as shown in
.