Installation Steps
4.3.1
Preparation before Main Machine Installation
1.
Before installing the door opener, please confirm that the door was installed correctly, please
ensure that the door can be manually operated smoothly, and the door limit stopper can
effectively prevent the door to continue moving.
2.
Please leave a 40 to 50 mm gap between the bottom of the door and the ground while
installing the electric lock. If an electric lock is not required, the distance between the door
bottom and the ground should be ≥20mm.
3.
The recommended mounting height of two main machines is around 300 to 800 mm above the
ground, and make sure that there are reliable fixed points for mounting brackets.
Cable bury
Please use two PVC pipes to bury the motor and power cables, as well as the control cables,
separately to ensure normal operation of the door opener and to protect the cable from damage.
The motor and power cables are routed via one PVC pipe, while the control cables are routed
through the other.
Mounting brackets fixing
To install the ZK-SW400DC main machines firmly, it is recommended to use the expansion screws to
fix the mounting brackets.
4.3.2
Accessory Installation
Before installing the main machines, please install the wall bracket on the wall first, then fix the
connecting bracket, and finally install the front mounting bracket on the door.
Note:
Please detect by gradient before fixing to ensure that the front mounting bracket and the
connecting bracket are in the same level.