24
Quick Start Installation Guide
807042 v1.02 08.22 HydroTap G5 UltraCare Install Instructions
SECTION 13: Commissioning
13. Commissioning the HydroTap using the HydroTap Clean can
• Initial commissioning screen touch
Language option.
• Touch the appropriate button to select
the language and units of choice.
• Touch the back arrow to go back to
previous menu.
• In the previous menu, touch the arrow to
begin the commissioning process.
• Optional screen shown if the
commissioning was previously started but
not complete (Command Centre powered
off during process). Otherwise screen will
not be shown.
• Read the commissioning information,
touch the forward arrow to go to the next
screen.
• (Touch the back arrow to go back to
previous menu).
13.2 Select the language
13.1 Turn on the supplies & familiarise yourself with the system
• Connect the mains electrical power cable to the supply.
• Turn the power and water on and check for any leaks.
• Familiarise yourself with the operation of the tap and GUI screen in
preparation for use, see the user guide.