pg. 22 | Zenaji Australia Pty Ltd
4
INSTALL
Method 1: Adjusting installed battery voltage
1. Note down the voltage of the additional battery.
2. Charge or discharge the installed batteries using the power equipment to within ±0.5V
of the additional battery.
3. Leave for 10 minutes and recheck the installed battery voltage, repeat step 2 as
required.
4.
Turn off your power equipment.
5. Disconnect all installed batteries by switching the circuit breakers to
OFF
.
6. Ensure the additional battery circuit breaker is set to
OFF
.
7.
Connect the additional battery to the system using the specific requirements of your
system. Multiple additional batteries can be connected at once, so long as their voltages
are with ±0.5V of each other.
8.
Follow your power equipment instructions to finish connecting and commissioning the
battery system.
Method 2: Adjusting additional battery voltage
1. Note down the voltage of the installed batteries.
2.
Turn off your power equipment.
3. Disconnecting the installed batteries by either:
a. Switching the circuit breakers to
OFF
on the base of the batteries, or;
b. In some cases you may be required to disconnect the wires from the power
equipment, to do so switch the circuit breakers to
OFF
on the base of the batteries
and then disconnect the wires from the power equipment.
4. Ensure the additional battery circuit breaker is set to
OFF
.
5. Connect the additional battery to the power equipment. Multiple additional batteries
can be connected at once, so long as their voltages are with ±0.5V of each other.
6. With the installed batteries disconnected commission the additional battery, following
your power equipment instructions.
7. Charge or discharge the additional battery to within ±0.5V of the installed batteries.
8. Leave for 10 minutes and recheck the additional battery voltage, repeat step 2 as
required.
9.
Turn off your power equipment.
10. Disconnect the additional battery by switching the circuit breakers to
OFF
.
11. If disconnected as in step 3b, reconnect the wires for the installed batteries.
12.
Follow your power equipment instructions to finish connecting and commissioning the
battery system.
4.5
Battery Registration
Once installed the battery must be registered with Zenaji by the customer who purchased
the battery, to do so go to
www.zenaji.com
and fill out the
Customer Registration
form.
The installer is also required to fill out the
Installer Commission Report
as specified in
section 7 of this document.
Содержание Aeon A48-40-01
Страница 1: ...Aeon Battery A48 40 01 A48 40 02 Installation Manual Pty Ltd...
Страница 2: ......
Страница 25: ...Aeon Battery Installation Manual V1 2 JAN 2020 pg 25 6 TROUBLE...
Страница 31: ......
Страница 32: ......