JOHNSON CONTROLS
33
SECTION 3 - HANDLING, STORAGE, INSTALLATION AND REASSEMBLY
FORM 201.30-ICOM1 (519)
ISSUE DATE: 05/22/2019
3
Installing the Evaporator
Use the following instructions to install the evaporator
.
The lifting chains along the axis of the
evaporator/condenser shells should not
exceed 90° +/- 10°. A spreader bar may
be required to achieve the +/- 10°.
One chain is required per each lifting
point.
Use lifting chains with working load limit
each at least 40% of the total shell weight.
TABLE 5 -
EVAPORATOR DIMENSIONS (IN/MM)
SHELL CODE (PIN 5)
LENGTH
WIDTH
HEIGHT
B
96 (2438)
28.7 (729)
66.3 (1685)
C
120 (3048)
28.7 (729)
66.3 (1685)
D
144 (3658)
28.7 (729)
66.3 (1685)
NOTE:
Refer to
for the approximate weight and water capacity of the evaporator.
LD17751a
EVAPORATOR
Lifting
Holes
90° +/- 10˚
65°
Min.
Lifting
Holes
Lifting
Holes
FIGURE 11 -
RIGGING THE EVAPORATOR
1. Attach the rigging chains from the overhead lift to
the four lifting holes of the evaporator (two at the
top of each end sheet).
2. Lift the evaporator by means of an overhead lift to
the unit's final location on the floor or housekeep-
ing pad
.
For information about clearance requirements, refer to
Содержание YVWA
Страница 14: ...JOHNSON CONTROLS 14 FORM 201 30 ICOM1 519 ISSUE DATE 05 22 2019 THIS PAGE INTENTIONALLY LEFT BLANK...
Страница 64: ...JOHNSON CONTROLS 64 FORM 201 30 ICOM1 519 ISSUE DATE 05 22 2019 THIS PAGE INTENTIONALLY LEFT BLANK...
Страница 82: ...JOHNSON CONTROLS 82 FORM 201 30 ICOM1 519 ISSUE DATE 05 22 2019 THIS PAGE INTENTIONALLY LEFT BLANK...
Страница 130: ...JOHNSON CONTROLS 130 FORM 201 30 ICOM1 519 ISSUE DATE 05 22 2019 THIS PAGE INTENTIONALLY LEFT BLANK...
Страница 146: ...JOHNSON CONTROLS 146 FORM 201 30 ICOM1 519 ISSUE DATE 05 22 2019 THIS PAGE INTENTIONALLY LEFT BLANK...
Страница 152: ...JOHNSON CONTROLS 152 FORM 201 30 ICOM1 519 ISSUE DATE 05 22 2019 THIS PAGE INTENTIONALLY LEFT BLANK...
Страница 155: ...JOHNSON CONTROLS 155 NOTES...