62
GLOBAL
INDUSTRIES, INC.
Drag Conveyors
10230011
2016-06-14
Hand Slide Gate Assembly
Assembly
27
Optional
Field cut and remove a 35 1/2” [902 mm] length
segment from the intermediate bottom
as shown
below
. Center the cut between 36” [914 mm]
bolt centers. Position the slide gate in the
opening just cut. Bolt discharge hopper ends
to the intermediate bottom placing the hopper
underneath the slide gate. Shim as required.
use 3/8” bolts
and flange nuts
caulk as needed
D8 and D12 = 35 1/2” (+1/16” - 0) [902 mm]
D16 and D21 = 34 13/16” (+1/16” - 0) [885 mm]
INTERMEDIATE
INSPECTION SECTION
HAND SLIDE
GATE
SHIM
(not supplied)
SLIDE GATE
STIFFENER ANGLE
DISCHARGE HOPPER
GRAIN FLOW
DIRECTION