background image

WFC- SC(H) Series 

.

Installation

 

 

- 14 - 

 

5.3.2. Inside of Junction box wiring 

 In the Junction box there is a noise filter and some connecting terminals as  
 figure 5-3-2. 
 

Note1. All conductors must be from copper material. 
 Note2. All wiring must comply with local and national electrical code and regulation. 
 

 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 

Terminal marking 

Description 

L1, L2, L3,PE 

400VAC 3phase 50Hz primary power supply  

PE 

Ground line 

Output control signal to chilling/heating water pump 

CP 

Output control signal to cooling water pump 

P3A 

Output control signal to heat medium pump (normal open) 

P3B 

Output control signal to heat medium pump (normal close) (Option) 

CTF 

Output control signal to cooling tower fan (Option) 

CM1 

Output signal common circuit 

Not Use 

Not Use 

Error signal from chilling/heating water pump 

Error signal from cooling water pump 

Error signal from cooling tower fan 

Error signal from heat medium pump 

Not Use 

Not Use 

CM2 

Error signals common circuit 

S3, S4 

Requirement heat medium output signal (Option) 

 

 

8 COM2

S3 S4

Noise filter

 

power supply terminal

 

Error signal input terminal

 

Control signal output  terminal

 

Extra control signal output terminal

 

connecting terminal

 

 

Connect the conductor by adjusting the 

 

    symbol (3,4,5,6,CM2) with figure 5-2-1 .

 

 

These are input terminal to the chiller.

 

 

Attention!

 

You must not give any voltage on to  
these  terminals.

 

 

Connect  the conductor by adjusting the 

 

    symbol (P,CP,P3A,CM1) with figure 5-2-1 .

 

 

These are output terminal from the chiller .

 

 

Attention!

 

    Do not exceed 24VAC, 60VA as shown in Figure 5-2-1.

 

 

 

 

Connect the 400VAC 3phase 50Hz power

 

    supply. Connect the ground conductor to PE.

 

 

 

 

Circuit breaker and over -current protection 

 

     must be supplied externally by others.

 

Figure 5-3-2

 

 P    CP   P3A   P3B   CTF  CM1

 

 L1      L2      L3   

Содержание WFC-SC Series

Страница 1: ...WFC SC H Chiller Chiller Heater 2 Installation WFC SC H 10 20 30 50 Version 11 1...

Страница 2: ...Electrical Wiring 5 1 Electrical system diagram 12 5 2 Electrical connection of auxiliary equipment 12 5 3 Junction box electrical wiring 13 5 3 1 Location of Junction box 13 5 3 2 Inside of Junction...

Страница 3: ...impact 3 Do not attempt to start the system without supervision from a Yazaki authorized service agent 1 2 Receiving When the absorption chiller heater is delivered to site inspect it for transit dam...

Страница 4: ...possible to use a crane for lifting a fork lift truck may be utilized In the event a crane or forklift cannot be used and the machine must be manhandled into position minimum dimensions for maneuver...

Страница 5: ...f the recommended service clearances cannot be provided as indicated the chiller heater should not be installed Figure 3 Table of Clearances Installation Area Maintenance Clearances Model WFC SC H A B...

Страница 6: ...distribution of working fluids internal to the machine to be impaired poor cooling performance will result 3 4 Placement For SC H 10 20 30 When the chiller heater is finally positioned on its foundati...

Страница 7: ...indicated in figure 9 to obtain longitudinal and transverse level Should the installation comprise more than one chiller heater located side by side it is important that all machines be individually l...

Страница 8: ...er temperatures during commissioning and maintenance procedures All piping should be properly aligned and graded to a drain valve to permit complete drainage of the system Properly located air vents s...

Страница 9: ...7 Do not exceed 588 kPa in the water heat medium circuit Figure 10 Typical piping system diagram WFC SC20 SH20 WFC SC30 SH30 WFC SC50 WFC SC10 SH10 Cooling Tower P P P P P P Air vent Air vent Drain Ch...

Страница 10: ...it install purge valves to expel trapped air Valve Thermometer Wells Chiller Heater Chiller Heater Chilled hot water pump Fan coil Fan coil Expansion tank Closed System Open System Water supply Cister...

Страница 11: ...ater circuit 4 3 Cooling Water Piping Cooling water to the absorption chiller heater is required at a temperature of 31 C or less during cooling operation It is also imperative that cooling water less...

Страница 12: ...eater warranty 4 4 Heat Medium Piping The heat medium pipe work will most likely be a closed system Accordingly since temperature of the heat medium may operate as high as 95 C with a standard inlet 8...

Страница 13: ...ote 4 Connect to Junction Box Note 5 In case of using 3 wayvalve Note 6 CTS P3A RT1 CM1 3 3way valve RT1 THR1 P SW1 RT2 THR2 CP SW2 RTF THRF SWF RT3 THR3 P3A SW3 RT3 LMT1 SWV RTV Do not exceed 24VAC 6...

Страница 14: ...cation of Junction box Junction box is located left bottom of the Chiller refer to figure 5 3 1a WFC SC H 10 20 30 WFC SC50 Junction box is located rear bottom of the Chiller refer to figure 5 3 1b Fi...

Страница 15: ...ing water pump 4 Error signal from cooling water pump 5 Error signal from cooling tower fan 6 Error signal from heat medium pump 7 Not Use 8 Not Use CM2 Error signals common circuit S3 S4 Requirement...

Страница 16: ...ote switch Connect the dry contact signal according to Figure 5 4 2 Take off the 2 screw to open the cover Take off the front panel CB Figure 5 4 1 Control panel Attention You must not give any voltag...

Страница 17: ...WFC SC H Series Installation 16 5 4 3 Position of RUN REMOTE STOP Switch Adjust the Run Remote Stop switch to the position of the Remote RUN REMOTE STOP Switch Figure 5 4 3 Control Panel...

Страница 18: ...B Figure 5 5 1 typical connection L1 L2 L3 U V W TR1 TR3 TR14TR5 TR6 TR7 TR8 15 16 17 18 S14 S13 S12 S11 TR9TR10TR11TR12TR13 S1 S2 S5 S6 S8 S9 S10 R1 24VAC L1 L2 R2 R1 R2 GL RL Terminal marking Descri...

Страница 19: ...th substantial bleed off would be necessary to achieve this result in the cooling water circuit If such water quality in supply is not available under all circumstances chemical treatment is required...

Страница 20: ...ler heater has been installed piped flushed leak tested and electrically wired as described in these instructions and in full compliance with all pertinent safety codes the Yazaki authorized distribut...

Страница 21: ...ipes 13 Make up and fill lines installed to the cooling tower and chilled hot water circuit 14 Air vent valves correctly installed 15 All water pipes cleaned flushed filled and leak tested ready for o...

Отзывы: