3.2 Minimum Maintenance Clearances 

 
The  minimum  space  and 
clearance 

requirements 

shown  in  figure  3  must  be 
provided 

around 

each 

chiller-heater 

unit 

to 

facilitate 

installation, 

commissioning 

and 

procedures  in  maintenance. 
The clearances shown in the 
table below apply to the CH-
K  30  through  to  the  CH-
K100  machines. 

If  the 

system  is  a  multi-module 
configuration  where  chiller-
heaters  will  be  placed  side-
by-side, 

the 

clearances 

recommended 

must 

still 

apply.  If  the  recommended 
service clearances cannot be 
provided  as  indicated,  the 
chiller-heater  should  not  be 
installed.  

Figure 3 

 

  Table of Clearances 

Installation Area 

Maintenance Clearances 

 

Model 

WFC-SC(H)

 

 

 

Front 

Back 

Left side 

Right side 

10 

3,575 

2,885 

1,000 

1,000 

700 

700 

20 

3,540 

2,860 

1,000 

1,000 

700 

700 

30 

3,780 

3,180 

1,000 

1,000 

700 

700 

50 

4,060 

3,185 

1,000 

1,000 

700 

700 

 

3.3 Foundation 

Mount  the  absorption  chiller-heater  on  a  level  foundation  constructed  of  non-
combustible materials, capable of supporting the operating weight of the machinery. 
This particularly applies to roofs, if that is where installation is contemplated. 
 
Be  sure  the  roof  is  able  to  support  the  chiller-heater,  cooling  tower,  pumps  and 
associated  piping  (refer  Section 

1.  Specifications 

for  details).  It  is  additionally 

important that, if the equipment is to be placed on the roof of a building, it should be 
located  in  a  well  drained  area  and  at  least  two  meters  from  the  edge.  A  suitable 

Содержание WFC-SC Series

Страница 1: ...WFC SC H Chiller Chiller Heater 2 Installation WFC SC H 10 20 30 50 Version 11 1...

Страница 2: ...Electrical Wiring 5 1 Electrical system diagram 12 5 2 Electrical connection of auxiliary equipment 12 5 3 Junction box electrical wiring 13 5 3 1 Location of Junction box 13 5 3 2 Inside of Junction...

Страница 3: ...impact 3 Do not attempt to start the system without supervision from a Yazaki authorized service agent 1 2 Receiving When the absorption chiller heater is delivered to site inspect it for transit dam...

Страница 4: ...possible to use a crane for lifting a fork lift truck may be utilized In the event a crane or forklift cannot be used and the machine must be manhandled into position minimum dimensions for maneuver...

Страница 5: ...f the recommended service clearances cannot be provided as indicated the chiller heater should not be installed Figure 3 Table of Clearances Installation Area Maintenance Clearances Model WFC SC H A B...

Страница 6: ...distribution of working fluids internal to the machine to be impaired poor cooling performance will result 3 4 Placement For SC H 10 20 30 When the chiller heater is finally positioned on its foundati...

Страница 7: ...indicated in figure 9 to obtain longitudinal and transverse level Should the installation comprise more than one chiller heater located side by side it is important that all machines be individually l...

Страница 8: ...er temperatures during commissioning and maintenance procedures All piping should be properly aligned and graded to a drain valve to permit complete drainage of the system Properly located air vents s...

Страница 9: ...7 Do not exceed 588 kPa in the water heat medium circuit Figure 10 Typical piping system diagram WFC SC20 SH20 WFC SC30 SH30 WFC SC50 WFC SC10 SH10 Cooling Tower P P P P P P Air vent Air vent Drain Ch...

Страница 10: ...it install purge valves to expel trapped air Valve Thermometer Wells Chiller Heater Chiller Heater Chilled hot water pump Fan coil Fan coil Expansion tank Closed System Open System Water supply Cister...

Страница 11: ...ater circuit 4 3 Cooling Water Piping Cooling water to the absorption chiller heater is required at a temperature of 31 C or less during cooling operation It is also imperative that cooling water less...

Страница 12: ...eater warranty 4 4 Heat Medium Piping The heat medium pipe work will most likely be a closed system Accordingly since temperature of the heat medium may operate as high as 95 C with a standard inlet 8...

Страница 13: ...ote 4 Connect to Junction Box Note 5 In case of using 3 wayvalve Note 6 CTS P3A RT1 CM1 3 3way valve RT1 THR1 P SW1 RT2 THR2 CP SW2 RTF THRF SWF RT3 THR3 P3A SW3 RT3 LMT1 SWV RTV Do not exceed 24VAC 6...

Страница 14: ...cation of Junction box Junction box is located left bottom of the Chiller refer to figure 5 3 1a WFC SC H 10 20 30 WFC SC50 Junction box is located rear bottom of the Chiller refer to figure 5 3 1b Fi...

Страница 15: ...ing water pump 4 Error signal from cooling water pump 5 Error signal from cooling tower fan 6 Error signal from heat medium pump 7 Not Use 8 Not Use CM2 Error signals common circuit S3 S4 Requirement...

Страница 16: ...ote switch Connect the dry contact signal according to Figure 5 4 2 Take off the 2 screw to open the cover Take off the front panel CB Figure 5 4 1 Control panel Attention You must not give any voltag...

Страница 17: ...WFC SC H Series Installation 16 5 4 3 Position of RUN REMOTE STOP Switch Adjust the Run Remote Stop switch to the position of the Remote RUN REMOTE STOP Switch Figure 5 4 3 Control Panel...

Страница 18: ...B Figure 5 5 1 typical connection L1 L2 L3 U V W TR1 TR3 TR14TR5 TR6 TR7 TR8 15 16 17 18 S14 S13 S12 S11 TR9TR10TR11TR12TR13 S1 S2 S5 S6 S8 S9 S10 R1 24VAC L1 L2 R2 R1 R2 GL RL Terminal marking Descri...

Страница 19: ...th substantial bleed off would be necessary to achieve this result in the cooling water circuit If such water quality in supply is not available under all circumstances chemical treatment is required...

Страница 20: ...ler heater has been installed piped flushed leak tested and electrically wired as described in these instructions and in full compliance with all pertinent safety codes the Yazaki authorized distribut...

Страница 21: ...ipes 13 Make up and fill lines installed to the cooling tower and chilled hot water circuit 14 Air vent valves correctly installed 15 All water pipes cleaned flushed filled and leak tested ready for o...

Отзывы: