Installation and Operation Guide SOLECTRIA® PVI 25TL-208, PVI 50TL-480 and PVI 60TL-480
DOCR-071030-A (10/7/2022)
Page 64 of 131
termination. Ensure the switch is in the OFF position for all other inverters in the daisy chain, including
the one where the Ethernet Network Card is installed.
5.
The shield of the individual cables must be open (not connected to ground) on one end – the other end
of the shield must be grounded.
WARNING
Risk of Electric Shock:
Make sure all shield wires are properly secured and insulated to prevent shorting to any
other components inside the inverter. Failure to follow this installation practice will increase lightning surge
damage to the inverter and will void the warranty.
6.
Close the wiring box.
7.
Reconnect the AC and DC power and turn the inverter on when it is safe.
8.
Configure the Inverter Modbus ID and Baud rate.
4.
User Interface
This section is intended to orient the user with the inverter interface prior to turning the system on and
commissioning.
Description of the Interface
The inverter’s user interface screen mainly consists of the LCD screen, four LED status indicator lights, a buzzer,
and four user keys, as shown in Figure 4-1.
POWER
RUN
GRID
FAULT
Figure 4-1 User Interface
The LCD panel includes a screen-saver function to increase the service life of the display. If there is no user activity
or operation (key press) for greater than 1 minute, the display will enter the screen-saving mode to protect the
screen and prolong the service life.
During normal inverter operation, a key press or any warnings or system faults that may occur will cause the LCD
to exit screen-saver mode.