Release 2.2
23
Section 2. Installation
Introduction
This section provides recommendations and procedures for inspecting, installing,
and testing the power supply.
Basic Setup Procedure
See
Table 2.1
for a summary of the basic setup procedure and an overall view of the
subsections in
Section 2
. Use the procedure as a quick reference if you are familiar
with the installation requirements for the power supply. If you want more
information, each step in the procedure refers to subsequent sections which contain
more details. Execute each step in the sequence given.
Table 2.1
Basic Setup Procedure
See
Section 3, “Operation”
for instructions about front panel operation, OVP, OTP,
shutdown, and using multiple supplies, plus you will find remote programming and
monitoring described there.
Step # Description Action
Reference
1
Inspection
Perform an initial physical
inspection of the supply.
“Inspection, Cleaning, and
Packaging” on page 24
2
Installation
Install the supply (bench or rack
mount), ensuring adequate
ventilation.
“Location, Mounting and
Ventilation” on page 27
3
Input Power
Connect AC input power.
“AC Input Power” on
page 28
4
Test
Perform functional tests for
voltage mode operation, current
mode operation, and front panel
controls.
“Functional Tests” on
page 30
5
Load
Connect the load.
“Load Connection” on
page 32
6
Sensing
Connect sensing lines.
“Local and Remote
Sensing” on page 35
Содержание XKW 150-7
Страница 2: ......
Страница 3: ...Operating Manual for XKW 1000 Watt Series Programmable DC Power Supply ...
Страница 15: ...Features and Specifications Front Panel Controls Release 2 2 13 Figure 1 1 Power Supply Front Panel ...
Страница 24: ...Features and Specifications Specifications 22 Operating Manual for XKW 1kW Series Power Supply ...
Страница 38: ...Installation Local and Remote Sensing 36 Operating Manual for XKW 1kW Series Power Supply ...
Страница 56: ...Operation Using Over Temperature Protection OTP 54 Operating Manual for XKW 1kW Series Power Supply ...
Страница 59: ......