Installation
System 182-XT-4
3 - 18
ba75753e06
12/2014
Materials required
1 x SNCIQ or SNCIQ/UG connection cable (see
chapter 10 A
)
Wire end sleeves for 0.75 mm2 wire cross-section with matching
crimping tool
1 x cable gland, matched to the cable diameter (see section 3.8 on
page 3-33).
Tools
Cable stripping knife
Wire stripper
Phillips screwdriver
Small screwdriver.
Preparing the cable
ends
1
Cut off the cable to the required length.
2
Remove approx. 45 mm of cable insulation (in the case of the
SNCIQ/UG earth cable, remove both the inner and outer
insulation).
3
Only for the SNCIQ/UG earth cable:
strip the outer insulation for a further 35 mm.
4
Shorten the exposed shielding braid up to the cable sheath.
5
Shorten the two fillers (plastic inlays) up to the cable sheath.
6
Bare the red and green wires and fit them with wire end
sleeves.
7
Fit the filler stranded wire with a wire end sleeve.
Содержание DIQ/S 182-XT-4
Страница 6: ...Contents System 182 XT 4 0 4 ba75753e06 12 2014 ...
Страница 14: ...Safety System 182 XT 4 2 4 ba75753e06 12 2014 ...
Страница 68: ...Installation System 182 XT 4 3 54 ba75753e06 12 2014 ...
Страница 86: ...Operation System 182 XT 4 4 18 ba75753e06 12 2014 ...
Страница 92: ...The SETTINGS menu System 182 XT 4 5 6 ba75753e06 12 2014 ...
Страница 128: ...Maintenance and cleaning System 182 XT 4 7 2 ba75753e06 12 2014 ...
Страница 144: ...Technical data System 182 XT 4 9 12 ba75753e06 12 2014 ...
Страница 146: ...Accessories and options System 182 XT 4 10 2 ba75753e06 12 2014 ...
Страница 150: ...Appendix store separately if required System 182 XT 4 12 2 ba75753e06 12 2014 ...
Страница 151: ......