Sawmill Setup
Stationary Sawmill Setup
Sawmill Setup
WMdoc072619
3-1
3
SECTION 3 SAWMILL SETUP
3.1
Stationary Sawmill Setup
Prepare the site:
Area must be firm and level.
The cement pad should be rated to support 6350 lbs./sq.ft.
Use 5/8” diameter anchor bolts to secure feet.
Allow maneuvering room for operators, sawdust removal, log loading, and board
removal.
for stationary sawmill foot anchor locations.
sawmill with bed extension foot anchor locations.
NOTE:
Make sure the unit is level before securing. It
IS POSSIBLE
to twist the mill frame
by jacking one foot higher than the others.
WARNING!
Securely fasten the feet of a stationary sawmill to the floor
before operating the sawmill. Failure to do so may result in serious
injury or death.
1.
Unhook the carriage safety chain, located at the bottom of the vertical mast.
See Figure 3-1.
FIG. 3-1
sm0413
qs-06
Содержание LT35
Страница 127: ...Electrical Information Engine Harness Wiring D24 Electrical Information 35doc072619 9 5 9 3H1220 2 ...
Страница 128: ...Electrical Information Engine Harness Wiring D24 9 9 6 35doc072619 Electrical Information 3H1220 3 ...
Страница 129: ...Electrical Information Engine Harness Wiring D24 Electrical Information 35doc072619 9 7 9 3H1220 4 ...