Figure 7. Deck leveling
6.10 INSTALLATION FOR ALL MODELS
1.
Locate and install the center cover over the mechanical safety release connecting rod and
hydraulic line. Install using four (4), ¼" - 20 UNC x ¾" long hex head bolts, flat washers
and lock washers.
2.
Check to make sure that the safety release connecting rod does not rub or bind during
operation.
3.
Locate and install protective line covers over all air and hydraulic supply lines on the left
side base frame of the left main frame assembly.
4.
Using a rotary hammer drill and a ¼" concrete drill bit, drill all line cover locations.
Using the ¼" concrete nails supplied fasten the line covers to the floor.
5.
Install the approach ramps using ramp pins, washers, and cotter pins.
6.
Tighten
all bolts on crossmember(s).
7 OPERATING
INSTRUCTIONS:
7.1 RAISING THE LIFT:
1.
If the lift is equipped with Sliding Jack Beam(s) be sure that the Beam(s) are positioned
at the front or mid travel of the lift, fully down, with the risers removed and stored.
Never store Jack Beam(s) at the rear of the lift.
2.
Be sure that the lift is fully lowered before attempting to load or unload a vehicle.
Содержание SPACESAVER 9000 Series
Страница 21: ...21 of 31 11 PARTS MANUAL 11 1 SPACE SAVER ALIGNMENT...
Страница 24: ...24 of 31 11 3 SPACE SAVER SERVICE RUST PROOFER...
Страница 28: ...28 of 31 11 7 SPACE SAVER HYDRAULICS...
Страница 30: ...30 of 31 11 9 9 000 LB SPACE SAVER POWER PACK...