2.3 Preparing the Unit for Installation
Installing the External Sand Relief and Sample Outlet Flexline
Figure 9: External Sand Relief and Sample Outlet Flexline Installation
1.
Prior to installing the inFlow™ ACE to the pipeline, the external sand relief and sample outlet flexline must be installed.
DO NOT install or operate the unit without first installing the external sand relief and sample outlet flexline. The external sand
relief is a safety relief valve required for safe installation and operation of the unit. Failure to install the external sand relief and
sample outlet flexline prior to installation and operation could damage the unit, injure the operator, or allow product to free
flow unchecked.
2.
Lay the inFlow™ ACE on a smooth, clean surface.
3.
Wrap the exposed threads on the external sand relief with PTFE tape.
4.
Screw the external sand relief into emergency shutoff valve E (
5.
Screw the loose end of the sample outlet flexline into the elbow above the sample outlet (
).
Aligning the Lock Collar
6.
Determine the direction of product flow in the pipeline.
7.
Lay the inFlow™ ACE on a smooth, clean surface.
8.
If the collection head is not fully visible, gently pull the collection head out of the lubricator body.
Note that the lock collar must be loose in order to pull the collection head out of the lubricator body.
9.
Loosen the jam nut, and then turn the hanger (
or
). The opening in the collection head should face the
direction of product flow so that the flowing stream will pass through the opening.
10.
Tighten the jam nut on the collection head (
). The tightened jam nut and safety wire will prevent the
collection head from turning.
11.
Align the alignment indicator rod on the lock collar with the opening in the collection head. This should bring the lock
collar into alignment with the lockdown studs on the lubricator body.
15
IOM-189
MODEL: INFLOW™ ACE MANUAL INSERTION
REV: G