62
of
76
TECHNICIANS manual
13.
DECOMMISSIONING
13.1
Short machine downtime
"Short machine downtime" refers to a period of time
exceeding one working week.
If the machine is reactivated after this period, the
Qualified Technician must replace all the water contained
in the hydraulic circuits as indicated in par. "6.6 Water
replacement" on page 26.
All the scheduled maintenance operations must also
be performed - see par. "10.3.1 Scheduled maintenance"
on page 48.
13.2
Long machine downtime
"Long machine downtime" refers to a period of time
exceeding 30 working days.
In this case, it is necessary to disconnect the machine
by unplugging it from the power, hydraulic and gas
supply if required, and drain the internal circuits of all
the water.
To connect the machine after this period, follow the
procedures for the commissioning of the machine.
14.
DISMANTLING
To dismantle the machine, follow the machine instal-
lation procedure in reverse; refer to chap."5. INSTALLA-
TION" on page 18 .
All the disassembled components must be sorted
out by material so as to facilitate the later disposal at
authorized collection centers, as indicated in section."15.
DISPOSAL" on page 63.