background image

8

EN

DEFENDER

 100-200 WHN

DEFENDER 

100-200 EHN

3.2.4. VERTICAL ASSEMBLY WITH USING INSTALATION HANDLES.

It is possible to assemble Defender to a wall vertically on both sides of the gate (with the motor on the bottom or on the top). 

For this option it is not important if you screw the handles down to the unit first and then screw the whole down to the wall or first attach the handles to the wall and then screw the curtain down to the 

handles. 

In the case of vertical assembly you should use the provided screws M10x80 and M8x80. 1, 2, or 3 handles should be attached with the use of screws (2) M8x80, through a backing strap (3) to the 

threaded sleeve (7) installed in the unit's guide bar (zoom A). The handle on the side of the exchanger's connection pins should be mounted on screws (2’) M10x80 slid in guide bars (as in the case 

of horizontal assembly), put a backing strap (3') and tighten the nut (4) (zoom B).

IMPORTANT:

 In case of vertical assembly the minimal distance between the device and the floor (150mm) for access to the water coil blowdown connection and the cable terminal should be 

provide.

A

B

B

A

B

A

7

min. 0,15m

IMPORTANT!

 The device is intended for the operation in dry rooms, eCDlusively. Thus, pay particular attention to the condensation of water vapour on engine elements, since it is not fitted 

for operating in humid environment.

IMPORTANT!

 The DEFENDER 100-200 air curtains are not intended for the installation:

● 

Outdoors;

● 

In humid rooms;

● 

In rooms categorised as explosive environments;

● 

In rooms with very high levels of dustiness;

● 

In rooms with aggressive atmosphere (due to the presence of copper and aluminium structural elements in the heat exchanger and electric heaters).

IMPORTANT! 

The DEFENDER 100-200 EH air curtains are not intended for the installation on suspended ceilings. 

3.3.   ASSEMBLY AND INSTALLATION GUIDELINES

CONNECTING OF HEATING MEDIUM 

Protect the heat exchanger terminal against the impact of the torque moment 1, when installing a pipeline transporting a heating medium. The weight of installed pipelines should not impose a load 

on the heater’s terminals.

IMPORTANT!

 Pay particular attention to the leak-tightness of connections, when filing the hydraulic system. Make sure that the water flowing from a leaky connection does not leak to the 

electric engine (at the vertical assembly)

IMPORTANT!

 It is recommended to use filters in the hydraulic system. It is recommended to clean/rinse the system, draining a few litres of water, prior to the connecting of hydraulic conduits 

(the supply conduits, in particular).

1

VENTING OF DEVICE/DRAINING OF HEATING MEDIUM 

The access to air vents / agent escapes is obtained by means of removing covers / hole plugs 1 and 2 depending on the way of assembling Defender. When using a 13 mm fork spanner or 

screwdriver you should loose the screw of an appropriate service valve:

 - venting: position A and B – service valve II with the flexible pipe, position C – service valve I,

 - escape: position A – service valve I, position B – service valve I, position C – service valve II.   

EXAMPLE OF HYDRAULIC SYSTEM

1. DEFENDERA 100-200 WH

2. VALVE WITH ACTUATOR

3. VENT VALVE

4. SHUT-OFF VALVE

5. FILTER

6. CIRCULATING PUMP

7. BOILER

SUPPL

Y

SUPPL

Y

RETURN

RETURN

Содержание DEFENDER 100 EHN

Страница 1: ...EN Technical documentation DEFENDER 100 200 WHN DEFENDER 100 200 EHN DR ver 1 9 07 2014 Check us on...

Страница 2: ...DEFENDER 100 200 WHN DEFENDER 100 200 EHN...

Страница 3: ...E 6 SERVICING 6 1 PROCEDURE IN CASE OF DEFECTS 6 2 COMPLAINT PROCEDURE 7 INDUSTRIAL SAFETY INSTRUCTION 8 TECHNICAL DATA 8 1 WATER AIR CURTAIN DEFENDER 100 200 WHN 8 2 ELECTRIC AIR CURTAIN DEFENDER 100...

Страница 4: ...after the completion of the assembly Prior to the commencing of any installation or maintenance work it is required to disconnect power supply and protect it against unintentional activation 2 STRUCT...

Страница 5: ...n air capacities up to 5000 m3 h The control of the electric motor as well as thermal protections of the winding has been coupled with the control system which resulted in increasing safety of operati...

Страница 6: ...itive effect on curtain operation doors or windows that are constantly open in the room thus creating a draft presence of awning roofs etc on the outer side of the door constant and open access to sta...

Страница 7: ...nsists in attaching the installation handles to the unit 1 at regular intervals as in OPTION I In order to do so you should slide 2 DR 1m 3 DR 1 5m or 4 DR 2m assembly screws 2 M10x80 in each of the t...

Страница 8: ...In rooms with very high levels of dustiness In rooms with aggressive atmosphere due to the presence of copper and aluminium structural elements in the heat exchanger and electric heaters IMPORTANT The...

Страница 9: ...e Connection to the electric system must be performed by a duly authorized and qualified person Wire passes are located on the back side of the curtain 1 control wire packing 2 power wire packing The...

Страница 10: ...draining a few litres of water prior to the connecting of hydraulic conduits the supply conduits in particular It is advised to use vent valves in the highest point of the system It is recommended to...

Страница 11: ...ice DEFENDER 100 200 WHN EHN Circumstances in which the defect occurred remarks on the bill of lading inventory issue condition of cardboard Should the casing be defective it is required to present ph...

Страница 12: ...TRUCTION Special instructions concerning safety IMPORTANT Prior to the commencing of any work related to the device it is required to disconnect the system secure it properly and wait until the fan st...

Страница 13: ...0 24 0 20 0 10 0 08 p kPa 2 38 2 04 1 73 1 45 1 73 1 44 1 17 0 93 1 15 0 91 0 69 0 49 0 63 0 43 0 13 0 09 Flow rate of air at 1470 m3 h speed 2 air velocity at the output 7 6 m s noise level 58 dB A...

Страница 14: ...14 3 78 3 19 2 65 2 16 2 68 2 17 1 72 1 31 1 7 1 28 0 91 0 59 Parametry DEFENDER 200 WHN Tz Tp C 90 70 80 60 70 50 60 40 Tp1 C 5 10 15 20 5 10 15 20 5 10 15 20 5 10 15 20 Flow rate of air at 4890 m3...

Страница 15: ...5 1 30 3 Flow rate of air at 1290 m3 h speed 1 air velocity at the output 6 7 m s noise level 52 dB A Pg kW 3 6 6 0 3 6 6 0 3 6 6 0 3 6 6 0 Tp2 C 12 7 18 4 17 7 23 4 22 7 28 4 27 7 33 4 Parametry DEFE...

Страница 16: ...dB A Pg kW 10 8 13 5 10 8 13 5 10 8 13 5 10 8 13 5 Tp2 C 14 2 17 4 19 2 22 4 24 2 27 4 29 2 32 4 Flow rate of air at 2500 m3 h speed 1 air velocity at the output 5 5 m s noise level 54 dB A Pg kW 10 8...

Страница 17: ...10 13 5 19 5 19 28 6 0 12 0 13 5 Maximum flow rate m h 1880 3570 4890 2150 3500 5000 Maximum temperature of heating medium C 95 Maximum working pressure MPa 1 6 Water volume dm 0 5 0 85 1 2 Diameter...

Страница 18: ...g 27 4 26 9 37 4 36 6 48 4 47 2 25 7 35 4 45 6 Engine IP 20 EN Heating output at the opening of the valve water temperature of 90 C and temperature of inlet air 15 C Heating output in the heating mode...

Страница 19: ...he equipment is at zero voltage 4 Cover or isolate nearby components that are still live To energize the system apply the measures in reverse order Components The machines consist for the most part of...

Страница 20: ...nting of any cover shut down the electric power at least by disconnecting the main switch Electrical connection of the thermostat door switch valve actuator or control panel is to be carried out befor...

Страница 21: ...f installation Place of installation Detailed description of defect Contact person Name and surname Telephone E mail This field must be filled if the complaint notification refers to the following equ...