49
Factory setting: "0"
The
"Commissioning/service"
operating mode must
be active (
"MNT"
illuminates).
1.
Use to select
"80"
.
2.
Press
SET
to confirm.
3.
Use to select the setting for the relevant coun-
try:
0 DE, CH, BE, LU
1 OT
2 FR, LU
3 GB
Only for LU
Select the setting
"0"
or
"2"
depending on the net-
work operator.
4.
Press
SET
to confirm.
Checking mains monitoring parameters (ENS), see
page 64.
Filling with distilled water and starting the system
Note
To make use of the waiting times that arise during
commissioning of the fuel cell module, carry out addi-
tional commissioning steps while you’re waiting.
This includes, for example:
■
Tightness tests
■
Visual inspections
■
Adjustments at the control unit
■
Instructing the system user
During these additional steps, watch the filling process
on the display and continue with it.
A
B
C
Fig. 40
0
1.
Remove the cover of filling aperture
A
.
0
2.
Remove the closure of vent aperture
C
.
0
3.
Undo funnel
B
and push it onto filling aperture
A
.
0
4.
Turn on the ON/OFF switch on the fuel cell mod-
ule.
0
5.
Use to select
"11"
.
0
6.
Press
SET
.
A dot will flash in
ITEM
(commissioning mode 1
enabled).
11
.
01
ITEM
STATE
Note
A fault has arisen if "n1", "n2" or "n3" is flashing in
STATE
.
0
7.
Use to select
"on"
.
0
8.
Press
SET
to confirm.
Commissioning, inspection, maintenance
Adjusting parameters for the mains monitor (ENS) (country setting)