21
7.11
Pressure losses of elements of fume-extraction system in using the boiler
VIADRUS K5
max. fan pressure 150Pa
Divided fume-extraction - flue gases
Ordering code
VIADRUS
code
DN
Name
Loss in Pa
20105
PPSB48
80
Elbow 45°
1.1
20107
PPSB98
80
Elbow 87°
1.7
20133
PPRM18
80
Pipe 1m
3.4
20111
PPSAS8
80
Plastic chimney head starr (complete)
2.5
Divided fume-extraction - suction
Ordering code
VIADRUS
code
DN
Name
Loss in Pa
20105
PPSB48
80
Elbow 45°
0.8
20107
PPSB98
80
Elbow 87°
1.2
20133
PPRM18
80
Pipe 1m
2.5
Concentrated fume-extraction
Ordering code
VIADRUS
code
DN
Name
Loss in Pa
20158
LPBK45
60/100
Elbow 45°
5.3
20160
LPBK95
60/100
Elbow 87°
7.5
20199
LPRK15
60/100
Pipe 1m
21.9
20197
LPZTK5
60/100
LIK T-piece for air supply
5
20235
LPASK5
60/100
LIK pipe part for facade fume-extraction
10.5
20221
DPDS45
60/100
Roof extension (complete)
29.8
7.12
Commissioning the boiler
The whole installation has to comply with regulations related to this equipment. The boiler has to be compatible
with the local connection conditions (check parameters of the boiler with the date on the name-plate).
Commissioning the boiler may be only performed by organizations nominated for this activity and trained
by the manufacturer. Minimum pressure in the heating system is 0.8 bar. It is necessary to check all shutters and
check that no gas escapes. Connect the boiler to the electric power supply network. Check the gas distribution
behind the gas valve. Check functionality of the safety valve. Further it is necessary to check the motion of the
pump. Check functionality of the three-way valve (if used). During running the boiler it is necessary to check
exhaust of condensate both from the boiler, and eventually from the liner.
Upon the first commissioning the boiler it is necessary to train the user in accordance with this manual
and hand over the manual to the user with a confirmation of commissioning.
Further it is necessary to:
-
check the revision before commissioning,
-
check the tightness of water escape,
-
check regulation and safety elements.
Production settings of the emission value of the boiler:
CO
2
– minimum boiler power 9,2 %,
– nominal boiler power 9,2 %,
Comparative conditions 15 °C and 1013,25 mbar, dry gas
Concrete measured values depend on type of connection of combustion air supply and flue gases exhaust to the
given consumer.
Set values CO
2
have to be observed.
Содержание VIADRUS K 5
Страница 1: ...1 VIADRUS K 5 Manual for boiler operation and installation GB_2016_42 GB_2016_47 ...
Страница 19: ...19 7 9 Connection of the system LIK 60 100 1 Flange 60 100 2 Screw M4 x 12 ...
Страница 30: ...30 ...
Страница 32: ...VIADRUS K 5 VIADRUS a s Bezručova 300 E mail CZ 735 81 Bohumín info viadrus cz www viadrus cz ...