Commissioning- instructions for contracting service organization
Boilers commissioning can only be done by contracting service organization authorized to do this
activity.
7.1
Verification before commissioning.
Before boilers commissioning there must be checked:
a) Heating system filling with water (thermomanometer check)
b) Heating system tightness
c) Connection to the chimney– must be approved by a chimney firm
d) Connection to the electricity network – must be approved by an authorized firm
The sockets are connected in a way making sure that the protection plug is at the top and the phase
conductor is connected to the left tube when viewed from the front. The same applies to the double
sockets.
7.2
Boilers commissioning
1. Fire the boilers (see chap.8.3.).
2. Bring the boiler to the necessary operating temperature. Recommended temperature of outlet heating
water is between 60 and 90°C.
3. Check again visually the boiler tightness.
4. Carry out the stoking test according to relevant standards (see the guarantee certificate)
5. Make the user acquainted with boiler operation (see chap.8).
6. Make a record in guarantee certificate.
Содержание HERCULES ECO
Страница 1: ...VIADRUS HERCULES ECO Manual for boiler operation and installation GB_2015_11 SD...
Страница 21: ...21 1 Partition of combustion chamber 2 Turbulators 3 Gripping of partitions Fig no 13a...
Страница 23: ...23 1 Partition of combustion chamber 2 Turbulators 3 Plate for ashes on the sheet metal Fig no 14a...
Страница 40: ...VIADRUS HERCULES ECO VIADRUS a s Bezru ova 300 E mail CZ 735 81 Bohum n info viadrus cz www viadrus cz...