Start a battery analysis.
Figure 11: UBAConsole: Starting a battery analysis. Click on the circled icon.
This opens up the Start a Battery Analysis dialog box:
Figure 12: Start a Battery Analysis dialog box: Entering analysis parameters.
There are three sections that need to be filled in before you can start the analysis.
Battery Parameters: Number of Cells and Capacity
Enter the number of cells (in series) and rated capacity of the battery. For battery packs the rated capacity and
nominal voltage should be printed on the pack. Calculate the number of cells by dividing the nominal pack voltage by
the nominal cell voltage.
Page 8
The UBA Let's Get Started Guide
Choose a BAR
Choose filename to store results.
Battery Parameters