Operations sequence
General instructions
43
cpg
.1
Fully SF6 gas insulated single and double busbar GIS switchgears up to 36 kV in accordance
with IEC Standards
IG-137-EN version 03; 24/06/2016
7.3.2 Earthing
Initial conditions
: feeder disconnector open
and earthing switch open.
Figure 7.18
Initial situation for
cpg.1-s1
cubicle
1. Connect the earthing switch by turning the lever
clockwise.
Figure 7.19
Lever turn detail
To open the earthing switch, proceed in reverse
order.
7.4
cpg.1-s2
cubicle
Figure 7.20
Initial situation for
cpg.1-s2
cubicle