Instructions générales
Installation
22
cpg.1
Fully SF6 gas insulated single and double busbar GIS switchgears up to 36 kV in accordance
with IEC Standards
IG-137-EN version 03 ; 23/06/2016
6 Installation
6.1 Unpacking the equipment
The switchgear
cpg.1
is supplied protected with a plastic
cover.
On receiving the equipment, check that the
goods supplied correspond to the order and
associated documentation. If this is not the
case, contact
Ormazabal
immediately.
The disassembly process for the equipment is as follows:
1.
Using a blade, cutter or similar tool, cut the cellophane
the cubicle is wrapped in.
2.
Remove the cellophane.
3.
Detach the white polystyrene corner pieces.
4.
Unscrew the fixings between the base and the pallet.
5.
Dispose of any waste in an environmentally-friendly
manner.
It is advisable to make a visual inspection of the equipment
to check whether it has suffered any damage in transit. If
damaged, contact
Ormazabal
immediately.
6.2 List of supplied materials
Along with the switchgear
cpg.1
a box is supplied with
all the material necessary for installation and correct
operation.
Depending on the cubicles which form part of the supply,
the assembly materials delivered will be some of the
following:
Description
Figure
Operating levers
Connecting terminals
T terminal
X-terminal
Toroidal current transformer s segregation
Bottom segregation
Earth plates
Bottom segregation plate
Right end plate
Top and bottom connection plate
Horizontal plate
Vertical plate
Decorative sides
Double busbar
High enclosure for busbar 2000 A
Single busbar with internal arc in busbar
compartment
Содержание Ormazabal cpg.1 Series
Страница 67: ......