valve cover as you are looking at the motor,
if using truck tank.
6. Leaving the unit in the preliminary position,
connect the ground cable to the unit battery,
check all fluid levels. Replace the front
access panel and close the unit hood.
7. Turn the Ignition switch on the control panel to
“
ON
”. The hood should be opened while the
ON sequence is inititated to check that the
fuel pump is energized. Wait 3-5 seconds for
the fuel pump to prime the fuel system. The
unit will start more quickly if the fuel pump is
manually pre-energized to prime the fuel
system. Start and run the unit for a few
minutes, then turn the machine off. Check
fuel connections for leaks, verify all
connections, and replace access panel and
close hood.
8. Move the unit into its final location for
mounting, while positioning the control trunk
line and all other connections.
9. Bolt the machine down with four ½” bolts
inserted from the bottom. See
Figures 4-1
and
Diagram 4.5
for location (
Diagram 4.5
shows mounting hole footprint as well).
10.
Start the unit and fully test all functions.
Warm the unit to full operating temperature.
After the unit has cooled, check all fluid
levels and add as needed.
Figure 4-5: Lifting Bail Location
NOTE
For guidance on machine start-up
procedure and control panel functions,
consult
Section 5, Operation
and
Appendix B
.
NOTE
For safety reasons the front access panel
and hood contain shut-off switches. The
front access panel will not allow the
machine to start if it is not in place, and
will shut down the machine if it is
removed while running. The machine will
also not start if the hood is open.
However, the machine will continue to
run if the hood is opened while the
machine is running. Consult
Section
1.11, Machine Canopy Access Safety
Switches
for further information on the
machine safety switches.
NOTE
It is recommended that the machine be
mounted on a vibration isolating material
such as 1/4” neoprene rubber pads.
Isolating Dampeners (Part Number
PR93969) are available by calling the
Vanair
®
Customer Service Department.
Содержание Air N Arc All-in-One Power Systems 300
Страница 10: ...TABLE OF CONTENTS AIR N ARC 300 SERIES ALL IN ONE POWER SYSTEM PAGE VIII P01080 003 BLANK PAGE...
Страница 14: ...GLOSSARY AIR N ARC 300 SERIES ALL IN ONE POWER SYSTEM PAGE XII 090010 OP_r0 BLANK PAGE...
Страница 50: ...SECTION 2 DESCRIPTION AIR N ARC 300 SERIES ALL IN ONE POWER SYSTEM PAGE 32 090010 OP_r0 BLANK PAGE...
Страница 54: ...SECTION 3 SPECIFICATIONS AIR N ARC 300 SERIES ALL IN ONE POWER SYSTEM PAGE 36 090010 OP_r0 BLANK PAGE...
Страница 74: ...SECTION 5 OPERATION AIR N ARC 300 SERIES ALL IN ONE POWER SYSTEM PAGE 56 090010 OP_r0 BLANK PAGE...
Страница 134: ...SECTION 8 DIAGRAMS AIR N ARC 300 SERIES ALL IN ONE POWER SYSTEM PAGE 116 090010 OP_r0 BLANK PAGE...
Страница 137: ...AIR N ARC 300 SERIES ALL IN ONE POWER SYSTEM SECTION 9 ILLUSTRATED PARTS LIST 090010 OP_r0 PAGE 119 NOTES...
Страница 174: ...SECTION 9 ILLUSTRATED PARTS LIST AIR N ARC 300 SERIES ALL IN ONE POWER SYSTEM PAGE 156 090010 OP_r0 BLANK PAGE...
Страница 182: ...APPENDIX A ADDITIONAL INFORMATION AIR N ARC 300 ALL IN ONE POWER SYSTEM PAGE 164 090010 OP_r0 BLANK PAGE...
Страница 198: ...APPENDIX B INSTRUMENT PANEL FUNCTIONS AIR N ARC 300 SERIES ALL IN ONE POWER SYSTEM PAGE 180 090010 OP_r0 BLANK PAGE...
Страница 202: ...APPENDIX C MAINTENANCE AND SERVICE LOG AIR N ARC 200 SERIES ALL IN ONE POWER SYSTEM PAGE 184 090010 OP_r0 BLANK PAGE...
Страница 203: ...BLANK PAGE...