14
Programming a New Test
The Optima has a pre-configured test for a basis to create new tests from. This is
programed into position 90 and is called “Master Program”.
It is recommended to clone program 90 into a new position before editing.
To do this:
1.
Turn the key on the Optima vT to the
program position
(vertical position).
2.
Open the
Test Setup screen
.
3.
Select the first tab “
Test”
. Select
Clone
. Once cloned, select the cloned
program from the menu. See Figure 15.
Figure 15: Clone Screen
Setup Screen
Select the
Step
tab to enter the Step screen, as shown in Figure 16. For each test, the
following parameters are recommended for programming a new test. In addition, select
the step type and duration.
Reference the Optima vT’s Owner’s guide for additional
information on setting up a new test.
Figure 16: Setup Screen