PCN 504819-000
Effective Date: June 29, 2010
PII 54863
Revision AD
5
13. Position black conductive tubes; shrink in place
Place black conductive tube over each phase and position at
dimension “I”.
Shrink in place starting at the end nearest to the center of the splice.
Black
Conductive Tubes
I
PILC
221
12. Mark OBT/ Insulation at “I”
Kit
I
HVSA-3-1581S
6-1/2” (165mm)
HVSA-3-1582S
7” (178mm)
HVSA-3-1583S
8” (203mm)
HVSA-3-1584S
8-1/2” (216mm)
OBT/Insulation
I
C
L
PILC
220
14. Clean OBTs
Using an approved solvent, clean the OBT/Insulation, as shown.
OBT/Insulation
Clean
PILC
222
15. Install SRM insert
Assemble SRM insert per box instructions. Spread the phases and
position the insert as shown.
Note:
The SRM insert is packaged inside the conductive breakout.
Copper Mesh
SRM Insert
PILC
SRM Insert
223
17. Clean lead sheath
Reclean lead sheath as shown using an approved solvent.
Clean
Lead Sheath
PILC
225
16. Trim excess SRM insert
Trim SRM insert to extend 1/8” (3mm) beyond each phase.
PILC
Trim SRM Insert
224